The precedence relation and duration (in days) of activities of project network are given in the table. The total float (in days) of activities “e” and “f”, respectively, are

      Activity

Predecessors

Duration (days)

a

-

2

b

-

4

c

a

2

d

b

3

e

c

2

f

c

4

g

d, e

5

                   

      (a) 0 and 4                                                          (b) 1 and 4

      (c) 2 and 3                                                          (d)  3 and 1