0 votes
51 views
asked in IM&OR by (215k points)

The precedence relation and duration (in days) of activities of project network are given in the table. The total float (in days) of activities “e” and “f”, respectively, are

      Activity

Predecessors

Duration (days)

a

-

2

b

-

4

c

a

2

d

b

3

e

c

2

f

c

4

g

d, e

5

                   

      (a) 0 and 4                                                          (b) 1 and 4

      (c) 2 and 3                                                          (d)  3 and 1

Please log in or register to answer this question.

Welcome to Q&A discussion forum, where you can ask questions and receive answers from other members of the community.

10.4k questions

274 answers

26 comments

15.2k users

...