In the construction of networks, dummy activities are introduced in order to:
0
votes
98
views
asked
Sep 6, 2017
in
IM&OR
by
chandu
(
215k
points)
In the construction of networks, dummy activities are introduced in order to:
(a) Compute the slack on all events
(b) Transfer resources, if necessary, during monitoring
(c) Clearly designate a precedence relationship
(d) Simplify the crashing plan
gate
1990
im&or
pert&cpm
Please
log in
or
register
to add a comment.
Please
log in
or
register
to answer this question.
Related questions
0
votes
0
answers
A dummy activity is used in PERT network to describe
asked
Sep 6, 2017
in
IM&OR
by
chandu
(
215k
points)
gate
1997
im&or
pert&cpm
0
votes
0
answers
Dummy activities are used in a network to
asked
Dec 30, 2017
in
im&or
by
chandu
(
215k
points)
ies-objectives-2
2000
im&or
pert&cpm
0
votes
0
answers
The total float (in days) of activities “e” and “f”, respectively, are
asked
Sep 6, 2017
in
IM&OR
by
chandu
(
215k
points)
gate
2014
im&or
pert&cpm
0
votes
0
answers
The number of activities that need to be crashed to reduced the project duration by 1 day is
asked
Sep 6, 2017
in
IM&OR
by
chandu
(
215k
points)
gate
2005
im&or
pert&cpm
0
votes
0
answers
The project activities, precedence relationships and durations are described in the table.
asked
Sep 6, 2017
in
IM&OR
by
chandu
(
215k
points)
gate
2010
im&or
pert&cpm
Welcome to Q&A discussion forum, where you can ask questions and receive answers from other members of the community.
Categories
All categories
GATE
(2k)
production
(409)
IM&OR
(175)
SOM
(145)
TOM
(164)
Engg Mechanics
(75)
Material Science
(53)
fm&turbo
(196)
HT
(152)
TD
(342)
MD
(111)
Engg-aptitude
(214)
IES Objectives-1
(1.8k)
IES Objectives-2
(2.8k)
IES Conventional-1
(655)
IES Conventional-2
(1.1k)
IAS Mains
(633)
IAS Prelims
(1.2k)
IES GS & Aptitude
(61)
Engineering Mathematics
(1)
Most popular tags
ies-objectives-2
gate
ies-objectives-1
production
iasprelims
ies-conventional-2
im&or
tom
fm
td
som
ies-conventional-1
iasmains
md
ppe
2009
2008
2014
2007
2005
10.4k
questions
274
answers
26
comments
15.2k
users
...