The project activities, precedence relationships and durations are described in the table. The critical path of the project is
Activity
|
precedence
|
Duration (in days)
|
P
|
-
|
3
|
Q
|
-
|
4
|
R
|
P
|
5
|
S
|
Q
|
5
|
T
|
R,S
|
7
|
U
|
R,S
|
5
|
V
|
T
|
2
|
W
|
U
|
10
|
(a) P-R-T-V (b) Q-S-T-V (c) P-R-U=W (d) Q-S-U-W