The project activities, precedence relationships and durations are described in the table. The critical path of the project is              

     

Activity

precedence

Duration  (in days)

P

-

3

Q

-

4

R

P

5

S

Q

5

T

R,S

7

U

R,S

5

V

T

2

W

U

10

      (a) P-R-T-V                     (b) Q-S-T-V                 (c) P-R-U=W                   (d)  Q-S-U-W