Given below are the data for a project network.                          

     

Activity

Immediately preceding

duration

A

--

3

B

---

5

C

A,B

5

D

A

4

E

C,D

4

F

A

4

G

A,B

6

 

      (a) Draw the network for the above project capturing the precedence relationships.

      (b) Find the critical path and its duration.