0 votes
80 views
asked in IM&OR by (215k points)

An electronic equipment manufacturer has decided to add a component sub-assembly operation that can produce 80 units during a regular 8-hour shift. This operation consists of three activities as below.                                                                                                                

Activity

Standard Time (min)

M. Mechanical assembly

12

E. Electric wiring

16

T. Test

3

For line balancing the number of work stations required for the activities M, E and T would respectively be

      (a) 2, 3, 1                        (b) 3, 2 1                      (c) 2, 4, 2                        (d) 2, 1, 3