0 votes
54 views
asked in IM&OR by (215k points)

A project has four activities P, Q, R and S as shown below.

     

Activity

Normal duration (days)

Predecessor

Cost slope (Rs./day)

P

3

-

500

Q

7

P

100

R

4

P

400

S

5

R

200

 

 

The normal cost of the project is Rs. 10,000/- and the overhead cost is Rs.200/- per day. If the project duration has to be crashed down to 9 days, the total cost (in Rupees) of the project is ____                                      

Please log in or register to answer this question.

Welcome to Q&A discussion forum, where you can ask questions and receive answers from other members of the community.

10.4k questions

274 answers

26 comments

15.3k users

...