A project with the following data is to be implemented:
Activity
|
Predecessors(s)
|
Duration
|
Cost (Rs/day)
|
A
|
-
|
2
|
50
|
B
|
-
|
4
|
50
|
C
|
A
|
1
|
40
|
D
|
B
|
2
|
100
|
E
|
A,B
|
3
|
100
|
F
|
E
|
2
|
60
|
(a) What is the minimum duration of the project?
(b) Draw a Gantt chart for the early schedule
(c) Determine the peak requirement of money and the day on which it occurs in above schedule