A project with the following data is to be implemented:  

     

Activity

Predecessors(s)

Duration

Cost (Rs/day)

A

-

2

50

B

-

4

50

C

A

1

40

D

B

2

100

E

A,B

3

100

F

E

2

60

 

      (a) What is the minimum duration of the project?

      (b) Draw a Gantt chart for the early schedule

      (c) Determine the peak requirement of money and the day on which it occurs in above schedule

Please log in or register to answer this question.