For a small project with five jobs, the following data is given     

     

Job

Immediate predecessors

Duration (days)

Mean

Std. deviation

A

B

C

D

E

-

-

A

A

B,C

10

5

16

12

15

2

1

2

2

1

 

      (i) Draw the project network in activity on arc mode

      (ii) Under PERT assumptions, determine the distribution of project duration.