What is the expected time of this activity?
0
votes
47
views
asked
Dec 31, 2017
in
im&or
by
chandu
(
215k
points)
A PERT activity has an optimistic time estimate of 3 days, a pessimistic time estimate of 8 days, and a most likely time estimate of 10 days. What is the expected time of this activity?
(a) 5.0 days (b) 7.5 days
(c) 8.0 days (d) 8.5 days
ies-objectives-2
2008
im&or
pert&cpm
Please
log in
or
register
to add a comment.
Please
log in
or
register
to answer this question.
Related questions
0
votes
0
answers
What is the additional time available for the performance of an activity in PERT and CPM calculated on
asked
Dec 31, 2017
in
im&or
by
chandu
(
215k
points)
ies-objectives-2
2008
im&or
pert&cpm
0
votes
0
answers
What is the expected time of the activity?
asked
Dec 31, 2017
in
im&or
by
chandu
(
215k
points)
ies-objectives-2
2005
im&or
pert&cpm
0
votes
0
answers
The earliest expected occurrence time (TE) for event 50 is:
asked
Dec 31, 2017
in
im&or
by
chandu
(
215k
points)
ies-objectives-2
2008
im&or
pert&cpm
0
votes
0
answers
The expected time of the activity would be
asked
Dec 30, 2017
in
im&or
by
chandu
(
215k
points)
ies-objectives-2
2002
im&or
pert&cpm
0
votes
0
answers
PERT is activity oriented and CPM is
asked
Dec 31, 2017
in
im&or
by
chandu
(
215k
points)
ies-objectives-2
2008
im&or
pert&cpm
Welcome to Q&A discussion forum, where you can ask questions and receive answers from other members of the community.
Categories
All categories
GATE
(2k)
IES Objectives-1
(1.8k)
IES Objectives-2
(2.8k)
tom
(488)
md
(417)
som
(393)
material science
(345)
production
(703)
im&or
(472)
robotics
(1)
mechatronics
(4)
engg mechanics
(5)
IES Conventional-1
(655)
IES Conventional-2
(1.1k)
IAS Mains
(633)
IAS Prelims
(1.2k)
IES GS & Aptitude
(61)
Engineering Mathematics
(1)
Most popular tags
ies-objectives-2
gate
ies-objectives-1
production
iasprelims
ies-conventional-2
im&or
tom
fm
td
som
ies-conventional-1
iasmains
md
ppe
2009
2008
2014
2007
2005
10.4k
questions
274
answers
26
comments
15.3k
users
...