A PERT activity has an optimistic time estimate of 3 days, a pessimistic time estimate of 8 days, and a most likely time estimate of 10 days. What is the expected time of this activity?                

(a) 5.0 days                     (b) 7.5 days

(c) 8.0 days                     (d) 8.5 days