The expected time of the activity would be
0
votes
121
views
asked
Dec 30, 2017
in
im&or
by
chandu
(
215k
points)
The three time estimates of a PERT activity are : optimistic time = 8 min, most likely time 10 min and pessimistic time = 14 min. The expected time of the activity would be
(a) 10.00 min (b) 10.33 min
(c) 10.66 min (d) 11.00 min
ies-objectives-2
2002
im&or
pert&cpm
Please
log in
or
register
to add a comment.
Please
log in
or
register
to answer this question.
Related questions
0
votes
0
answers
What is the expected time of this activity?
asked
Dec 31, 2017
in
im&or
by
chandu
(
215k
points)
ies-objectives-2
2008
im&or
pert&cpm
0
votes
0
answers
What is the expected time of the activity?
asked
Dec 31, 2017
in
im&or
by
chandu
(
215k
points)
ies-objectives-2
2005
im&or
pert&cpm
0
votes
0
answers
If the activity time is 11 weeks then the total float will be
asked
Dec 30, 2017
in
im&or
by
chandu
(
215k
points)
ies-objectives-2
1998
im&or
pert&cpm
0
votes
0
answers
The expected time (te) of a PERT activity in terms of optimistic time (t0), pessimistic (tp) and most likely time (tL)
asked
Sep 6, 2017
in
IM&OR
by
chandu
(
215k
points)
gate
2009
im&or
pert&cpm
0
votes
0
answers
For the network shown in the given figure the earliest expected completion time of the project is
asked
Dec 30, 2017
in
im&or
by
chandu
(
215k
points)
ies-objectives-2
2001
im&or
pert&cpm
Welcome to Q&A discussion forum, where you can ask questions and receive answers from other members of the community.
Categories
All categories
GATE
(2k)
IES Objectives-1
(1.8k)
IES Objectives-2
(2.8k)
tom
(488)
md
(417)
som
(393)
material science
(345)
production
(703)
im&or
(472)
robotics
(1)
mechatronics
(4)
engg mechanics
(5)
IES Conventional-1
(655)
IES Conventional-2
(1.1k)
IAS Mains
(633)
IAS Prelims
(1.2k)
IES GS & Aptitude
(61)
Engineering Mathematics
(1)
Most popular tags
ies-objectives-2
gate
ies-objectives-1
production
iasprelims
ies-conventional-2
im&or
tom
fm
td
som
ies-conventional-1
iasmains
md
ppe
2009
2008
2014
2007
2005
10.4k
questions
274
answers
26
comments
15.3k
users
...