The expected time (te) of a PERT activity in terms of optimistic time (t0), pessimistic (tp) and most likely time (tL) is given by
(a) $t_{e}=\frac{t_{o}+4t_{l}+t_{p}}{6}$
(b) $t_{e}=\frac{t_{o}+4t_{p}+t_{L}}{6}$
(c) $t_{e}=\frac{t_{o}+4t_{L}+t_{p}}{3}$
(d)$t_{e}=\frac{t_{o}+4t_{p}+t_{L}}{3}$