0 votes
114 views
asked in im&or by (215k points)
edited by

Consider the above network. Activity times are given in number of days. The earliest expected occurrence time (TE) for event 50 is:                                    

(a) 22          (b) 23           (c) 24      (d) 25                                  

Please log in or register to answer this question.

Welcome to Q&A discussion forum, where you can ask questions and receive answers from other members of the community.

10.4k questions

274 answers

26 comments

15.3k users

...