Which one of the following statements is not correct?
(a) PERT is activity oriented and CPM is event oriented
(b) In PERT, three time estimates are made, whereas in CPM only one time estimate is made
(c) In PERT slack is calculated whereas in CPM floats are calculated
(d) Both PERT and CPM are used for project situations