Which one of the following statements is not correct?
(a) PERT is probabilistic whereas CPM is deterministic
(b) In PERT slack on various events is calculated whereas in CPM floats are calculated
(c) Critical path in a network is the path on which events have no slack
(d) More than four dummy activities cannot be used in a PERT network