Match List – I with List – II and select the correct answer using the code given below the lists:
List – I List – II
(Type of Job) (Appropriate Method – study Technique)
A. Complete sequence of operations 1. Flow diagram
B. Factory layout : movement of materials 2. Flow process chart
C. Factory layout : movement of workers 3. Multiple activity chart
D. Gang work 4. String diagram
A B C D
(a) 4 3 2 1
(b) 2 1 4 3
(c) 4 1 2 3
(d) 2 3 4 1