Match List I (Production Control Function) with List II (Explanation) and select the correct answer using the code given below the Lists:                                      

List I

(a) Bill of Materials (BOM)

(b) Capacity Resource Planning (CRP)

(c) Material Requirement Planning (MRP)

(d) Master Production Schedule (MPS)

List II

1.   A technique for determining the quantity and timing of dependent demand items

2.   A technique for determining personnel and equipment capacities needed to meet the production objective

3.   Specifies what end items are to be      produced and when

4.   The part numbers & quantity required      per assembly

Codes:

  A       B         C         D

(a) 4        1          2          3

(b) 3        2          1          4

(c) 4        2          1          3

(d) 3        1          2          4      