0 votes
85 views
asked in im&or by (215k points)

  Match List I (PPC functions) with List II (Activity) and select the correct answer using the codes given below the Lists

List I                                

(a) Capacity planning

(b) Shop floor control

(c) Master production schedule

(d) Material requirement planning

List II

1.   Listing products to be assembled and when to be delivered

2.   Rescheduling orders based on production priorities

3.   Closure tolerances

4.   Monitor progress of orders and, report their status

5.   Planning of labour and equipment

Codes;

A         B         C         D

(a) 1        4          3          2

(b) 5        2          1          4         

(c) 1        2          3         4

(d) 5        4          1          2       

Please log in or register to answer this question.

Welcome to Q&A discussion forum, where you can ask questions and receive answers from other members of the community.

10.4k questions

274 answers

26 comments

15.3k users

...