 Match List I with List II and select the correct answer:                                  

List I (Files in MRP)

(a) Master production schedule

(b) Bills of materials

(c) Inventory records

List II (Inputs required)

1. Scheduled receipts

2. Units costs and discounts

3. Production capacity

4. Product structure

Codes:

A         B        C                      A    B        C

(a) 4        1          3          (b) 3     4          2

(c)3         4          1          (d) 4    3          1

Please log in or register to answer this question.