0 votes
70 views
asked in im&or by (215k points)
If critical path of a project is 20 months with a standard derivative 4 months, What is the probability that the project will be completed in 24moths?             

(a) 15.85 %                     (b) 68.3 %

(c) 84.2 %                       (d) 95.50%