0 votes
43 views
asked in im&or by (215k points)

Estimated time  and variance of the activities ‘V’ on the critical path in a PERT network are given in the following table

Activity

V (days)

A

17

4

B

15

4

G

8

1

The probability completing the project in 43 days is                     

(a) 15.6%                                    (b) 50.0%

(c) 81.4%                                    (d) 90.0%

Please log in or register to answer this question.

Welcome to Q&A discussion forum, where you can ask questions and receive answers from other members of the community.

10.4k questions

274 answers

26 comments

15.3k users

...