0 votes
167 views
asked in im&or by (215k points)
edited by

For the network shown’ in the figure, the variance along the critical path is 4.

(

The probability of completion of the project in 24 days is

(a) 68.2%                        (b) 84.1%

(c) 95.4%                     (d) 97.7%

Please log in or register to answer this question.

Welcome to Q&A discussion forum, where you can ask questions and receive answers from other members of the community.

10.4k questions

274 answers

26 comments

15.3k users

...