Time estimates of an activity in a PERT network are Optimistic time $t_{0}=9$ days pessimistic time $t_{p}=21$ and most likely time $t_{m}=15days$. The approximates probability of completion of this activity is 13 days is
(a) 16 % (b) 34%
(c) 50% (d) 84%