Match List - I with List – II and select the correct answer using
List - I (Term)
(A) Dummy activity
(B) Critical path
(C) PERT activity
(D) Critical path method
List -II (Characteristics)
1. Follows distribution
2. It is built on activity-oriented diagram
3. Constructed only to establish sequence
4. Has zero total slack
Codes;
A B C D
(a) 3 4 1 2
(b) 4 2 3 1
(c) 3 4 2 1
(d) 4 2 1 3