Login
Remember
Register
Adapala's Forum
Home
Questions
Unanswered
Tags
Categories
Users
Ask a Question
Adapala
IES GS
Ask a Question
The critical path of a network is the path that:
0
votes
130
views
asked
Dec 31, 2017
in
im&or
by
chandu
(
215k
points)
The critical path of a network is the path that:
(a) Takes the shortest time
(b) Takes the longest time
(c) Has the minimum variance
(d) Has the maximum variance
ies-objectives-2
2005
im&or
pert&cpm
Please
log in
or
register
to add a comment.
Please
log in
or
register
to answer this question.
Related questions
0
votes
0
answers
In the network shown below the critical path is along
asked
Dec 30, 2017
in
im&or
by
chandu
(
215k
points)
ies-objectives-2
1996
im&or
pert&cpm
0
votes
0
answers
The critical path duration of the network (in days) is
asked
Sep 6, 2017
in
IM&OR
by
chandu
(
215k
points)
gate
2009
im&or
pert&cpm
0
votes
0
answers
The critical path, the project duration and the free float for activity A are, respectively
asked
Dec 31, 2017
in
im&or
by
chandu
(
215k
points)
ies-objectives-2
2017
im&or
pert&cpm
0
votes
0
answers
The critical path (CP) in the network is
asked
Sep 6, 2017
in
IM&OR
by
chandu
(
215k
points)
gate
2015
im&or
pert&cpm
0
votes
0
answers
Draw the network diagram and determine the critical path. Also determine the critical path time.
asked
Nov 9, 2017
in
im&or
by
chandu
(
215k
points)
ies-conventional-2
1990
im&or
industrial-engg
pert&cpm
Welcome to Q&A discussion forum, where you can ask questions and receive answers from other members of the community.
Categories
All categories
GATE
(2k)
IES Objectives-1
(1.8k)
IES Objectives-2
(2.8k)
tom
(488)
md
(417)
som
(393)
material science
(345)
production
(703)
im&or
(472)
robotics
(1)
mechatronics
(4)
engg mechanics
(5)
IES Conventional-1
(655)
IES Conventional-2
(1.1k)
IAS Mains
(633)
IAS Prelims
(1.2k)
IES GS & Aptitude
(61)
Engineering Mathematics
(1)
Most popular tags
ies-objectives-2
gate
ies-objectives-1
production
iasprelims
ies-conventional-2
im&or
tom
fm
td
som
ies-conventional-1
iasmains
md
ppe
2009
2008
2014
2007
2005
10.4k
questions
274
answers
26
comments
15.3k
users
...