 The following table lists the tasks in a project and the time duration for each task:

Task

Preceding task

Normal duration

(in weeks)

A

16

B

20

C

A

8

D

A

10

E

B, C

6

F

D, E

12

 

         The critical path, the project duration and the free float for activity A are, respectively

         (a) A-C-E-F; 42 weeks and 0 week

         (b) B-E-F; 42 weeks and 1 week

         (c) B-C-D-F; 50 weeks and 2 weeks

         (d) A-C-E-F; 50 weeks and 0 week