0 votes
40 views
asked in IM&OR by (215k points)

Following data refers to the activities of a project, where, node 1 refers to the start and node 5 refers to the end of the project

     

Activity

Duration (days)

1-2

2

2-3

1

4-3

3

1-4

3

2-5

3

3-5

2

4-5

4

      The critical path (CP) in the network is                            

      (a) 1-2-3-5                                                          (b) 1-4-3-5         

      (c) 1-2-3-4-5                                                       (d) 1-4-5

Please log in or register to answer this question.

Welcome to Q&A discussion forum, where you can ask questions and receive answers from other members of the community.

10.4k questions

274 answers

26 comments

15.3k users

...