Following data refers to an automat and a centre lathe, which are being compared to machine  batch of parts in a manufacturing shop

 

         Automat

     Center Lathe

Machine Set-up Time I min

             120

             30

Machine Set-up Cost in Rs/min

             800

             150

Machining Time per piece in min

             2

             5

Machining Cost in Rs/min

             500

             100

Automat will be economical if the batch side exceeds

(a) 28        (b) 32         (c) 61           (d) 75