A standard machine tool and an automatic machine tool are being compared for the production of a component. Following data refers to the two machines.
|
Standard Machine Tool
|
Automatic Machine Tool
|
Set Up time
|
30 min
|
2 hours
|
Machining time per piece
|
22 mm
|
5 mm
|
Machine rate
|
Rs.200/Hour
|
Rs.800/Hour
|
The breakeven production batch size, above which the automatic machine tool will be economical to use, will be
(a) 4 (b) 5 (c) 24 (d) 225