0 votes
50 views
asked in production by (215k points)

The following data is available for machining a component on a turret or center lathe: find out the total number of components to be machined to justify the use of turret lathe

 

TURRET LATHE

CENTER LATHE

Machining time per piece

              4 min

            14 min

Operator wages (Rs/hr)2.0

               2.0

               4.5

Machine overheads (Rs/hr)

               4.0

               2.5

Set up time

         3hrs/batch

         2hrs/batch

Please log in or register to answer this question.

Welcome to Q&A discussion forum, where you can ask questions and receive answers from other members of the community.

10.4k questions

274 answers

26 comments

15.2k users

...