0 votes
105 views
asked in IM&OR by (215k points)
Time study of an operator with a performance rating of 120% yield a time of 2 minutes. If the allowances of 10% of the total available time are to be given, then what is the standard time of operation?

            (a) 2.00 minutes          (b) 2.40 minutes

            (c) 2.64 minutes          (d) 2.67 minutes

Please log in or register to answer this question.

Welcome to Q&A discussion forum, where you can ask questions and receive answers from other members of the community.

10.4k questions

274 answers

26 comments

15.3k users

...