0 votes
183 views
asked in IM&OR by (215k points)
For a manual operation to study the total processing standard time using a chronometer, following observations were made:

         Processing time                          : 16 minutes

         Rating of the worker                  : 120%

         Personal allowance                     : 0.6 minutes

         Basic fatigue allowance             : 1.92 minutes

         Unavoidable delay allowance    : 1.08 minutes

         What is the standard operating time for the operation?

         (a) 16 minutes                (b) 17.92 minutes      

         (c) 21.52 minutes           (d) None of the above

Please log in or register to answer this question.

Related questions

0 votes
0 answers
0 votes
0 answers
0 votes
0 answers
Welcome to Q&A discussion forum, where you can ask questions and receive answers from other members of the community.

10.4k questions

274 answers

26 comments

15.3k users

...