For a manual operation, observed time data are given below:

            Recorded time                                    : 15 minute

            Rating of the worker               : 80%

            Personal allowance                  : 0.6 minute

            Basic fatigue allowance          : 0.8 minute

            Contingency work allowance : 1.2 minute

            Unavoidable delay allowance : 1.1 minute

            What is the standard time for the operation?

            (a) 16.4 minute                        (b) 17.5 minute

            (c) 18.5 minute                        (d) None of the above