0 votes
64 views
asked in IM&OR by (215k points)
For a manual operation, observed time data are given below:

            Recorded time                                    : 15 minute

            Rating of the worker               : 80%

            Personal allowance                  : 0.6 minute

            Basic fatigue allowance          : 0.8 minute

            Contingency work allowance : 1.2 minute

            Unavoidable delay allowance : 1.1 minute

            What is the standard time for the operation?

            (a) 16.4 minute                        (b) 17.5 minute

            (c) 18.5 minute                        (d) None of the above

Please log in or register to answer this question.

Welcome to Q&A discussion forum, where you can ask questions and receive answers from other members of the community.

10.4k questions

274 answers

26 comments

14.7k users

...