(i) Define ‘slack’. 5
(ii) A project consists of six activities. The precedence relationship of activities and the three time estimates of completion of activities in days are tabulated below:
Sl. No.
|
Activity
|
Immediate
Precedent
Activity
|
Estimate Time of Completion (days)
|
Optimistic
|
Pessimistic
|
Most likely
|
1
2
3
4
5
6
|
A
B
C
D
E
F
|
-
A
B
A
A
C,D,E
|
0.5
1.0
2.0
2.9
1.5
3.0
|
1.5
3.0
2.0
4.1
4.0
6.0
|
1.00
2.00
2.00
2.75
1.63
3.75
|
- Draw the arrow diagram.
- Which of the six activities is most uncertain?
- What is the probability that the project will be completed within 10 days? Refer the SND-chart (Cumulative Distribution Function for the Standard Normal Distribution) attached at the end.