(i) Define ‘slack’.                                                                                                                     5

(ii) A project consists of six activities. The precedence relationship of activities and the three time estimates of completion of activities in days are tabulated below:

Sl. No.

Activity

Immediate

Precedent

Activity

Estimate Time of Completion (days)

Optimistic

Pessimistic

Most likely

1

2

3

4

5

6

A

B

C

D

E

F

-

A

B

A

A

C,D,E

0.5

1.0

2.0

2.9

1.5

3.0

1.5

3.0

2.0

4.1

4.0

6.0

1.00

2.00

2.00

2.75

1.63

3.75

  1. Draw the arrow diagram.
  2. Which of the six activities is most uncertain?
  3. What is the probability that the project will be completed within 10 days? Refer the SND-chart (Cumulative Distribution Function for the Standard Normal Distribution) attached at the end.

Please log in or register to answer this question.

Related questions

0 votes
0 answers
0 votes
0 answers
0 votes
0 answers
asked Aug 31, 2017 in IM&OR by chandu (215k points)
Welcome to Q&A discussion forum, where you can ask questions and receive answers from other members of the community.

10.4k questions

274 answers

26 comments

15.3k users

...