0 votes
111 views
asked in IM&OR by (215k points)
edited by

The project network for manufacturing a product is given below with seven events (A–G) and eight activities. The estimates of optimistic, most likely and pessimistic times in day are shown as t0-tm-tp in that order, for each activity:

Determine the slack time for each activity.

Find the critical path.

Find the earliest possible project completion time.

Please log in or register to answer this question.

Welcome to Q&A discussion forum, where you can ask questions and receive answers from other members of the community.

10.4k questions

274 answers

26 comments

15.3k users

...