The project network for manufacturing a product is given below with seven events (A–G) and eight activities. The estimates of optimistic, most likely and pessimistic times in day are shown as t0-tm-tp in that order, for each activity:
Determine the slack time for each activity.
Find the critical path.
Find the earliest possible project completion time.