0 votes
35 views
asked in im&or by (215k points)
A PERT activity has an optimistic time estimate of 3 days, a pessimistic time estimate of 8 days, and a most likely time estimate of 10 days. What is the expected time of this activity?                

(a) 5.0 days                     (b) 7.5 days

(c) 8.0 days                     (d) 8.5 days

Please log in or register to answer this question.

Related questions

Welcome to Q&A discussion forum, where you can ask questions and receive answers from other members of the community.

10.4k questions

274 answers

26 comments

14.6k users

...