0 votes
113 views
asked in im&or by (215k points)
The three time estimates of a PERT activity are : optimistic time = 8 min, most likely time 10 min and pessimistic time = 14 min. The expected time of the activity would be                                           

(a) 10.00 min                  (b) 10.33 min

(c) 10.66 min                  (d) 11.00 min

Please log in or register to answer this question.

Welcome to Q&A discussion forum, where you can ask questions and receive answers from other members of the community.

10.4k questions

274 answers

26 comments

14.7k users

...