In a small engineering project, for an activity the optimistic time is 2 minutes, the most likely time is 5 minutes and the pessimistic time is 8 minutes. What is the expected time of the activity?
(a) 1 minutes (b) 5 minutes
(c) 8 minutes (d) 18 minutes