In a small engineering project, for an activity the optimistic time is 2 minutes, the most likely time is 5 minutes and the pessimistic time is 8 minutes. What is the expected time of the activity?

(a) 1 minutes                   (b) 5 minutes

(c) 8 minutes                   (d) 18 minutes