Which one of the following statements is not correct?                       

(a) PERT is probabilistic and CPM is deterministic

(b) In PERT, events are used and in CPM activities are used

(c) In CPM, the probability to complete the project in a given time-duration is calculated

(d) In CPM crashing is carried out