In PERT and CPM network the dummy activity
0
votes
63
views
asked
Dec 31, 2017
in
im&or
by
chandu
(
215k
points)
In PERT and CPM network the dummy activity
(a) Consumes time
(b) Consumes resources
(c) Is used to preserve the logic
(d) Is a real activity
ies-objectives-2
2010
im&or
pert&cpm
Please
log in
or
register
to add a comment.
Please
log in
or
register
to answer this question.
Related questions
0
votes
0
answers
A dummy activity is used in PERT network for:
asked
Dec 31, 2017
in
im&or
by
chandu
(
215k
points)
ies-objectives-2
2013
im&or
pert&cpm
0
votes
0
answers
A dummy activity is used in PERT network to describe
asked
Sep 6, 2017
in
IM&OR
by
chandu
(
215k
points)
gate
1997
im&or
pert&cpm
0
votes
0
answers
What is the additional time available for the performance of an activity in PERT and CPM calculated on
asked
Dec 31, 2017
in
im&or
by
chandu
(
215k
points)
ies-objectives-2
2008
im&or
pert&cpm
0
votes
0
answers
PERT is activity oriented and CPM is
asked
Dec 31, 2017
in
im&or
by
chandu
(
215k
points)
ies-objectives-2
2008
im&or
pert&cpm
0
votes
0
answers
PERT is probabilistic whereas CPM is
asked
Dec 31, 2017
in
im&or
by
chandu
(
215k
points)
ies-objectives-2
2010
im&or
pert&cpm
Welcome to Q&A discussion forum, where you can ask questions and receive answers from other members of the community.
Categories
All categories
GATE
(2k)
IES Objectives-1
(1.8k)
IES Objectives-2
(2.8k)
tom
(488)
md
(417)
som
(393)
material science
(345)
production
(703)
im&or
(472)
robotics
(1)
mechatronics
(4)
engg mechanics
(5)
IES Conventional-1
(655)
IES Conventional-2
(1.1k)
IAS Mains
(633)
IAS Prelims
(1.2k)
IES GS & Aptitude
(61)
Engineering Mathematics
(1)
Most popular tags
ies-objectives-2
gate
ies-objectives-1
production
iasprelims
ies-conventional-2
im&or
tom
fm
td
som
ies-conventional-1
iasmains
md
ppe
2009
2008
2014
2007
2005
10.4k
questions
274
answers
26
comments
14.6k
users
...