0 votes
54 views
asked in im&or by (215k points)
A dummy activity is used in PERT network for:                   

(a) Precedence relationship

(b) Necessary time delay

(c) Resource restriction

(d) Resource idleness

Please log in or register to answer this question.

Welcome to Q&A discussion forum, where you can ask questions and receive answers from other members of the community.

10.4k questions

274 answers

26 comments

14.6k users

...