Consider the following statements in respect of PERT and CPM:      

1.   PERT is event-oriented while CPM is activity-oriente(d)

2.   PERT is probabilistic while CPM is deterministi(c)

3. Levelling and smoothing are the techniques related to resource scheduling in CPM.

Which of the statements given above are correct?

(a) 1, 2 and 3                  (b) Only 1 and 2

(c) Only 2 and 3             (d) Only 1 and 3

Please log in or register to answer this question.