0 votes
36 views
asked in im&or by (215k points)

Six jobs are to be processed on two milling machines. All of them follow the same machine sequence. Determine the optimal job sequence and minimum total expected time from the data given below

              Job No.

1

2

3

4

5

6

Processing

Time(Min)

M/c 1

5

4

2

5

6

3

M/c 2

7

3

8

3

1

5

        

Please log in or register to answer this question.

Welcome to Q&A discussion forum, where you can ask questions and receive answers from other members of the community.

10.4k questions

274 answers

26 comments

14.7k users

...