asked in im&or by (215k points)

Consider the following jobs and their processing times at corresponding machines:-

Job

Duration (Hours)

m/c 1

m/c 2

m/c 3

 

t1

t2

t3

A

13

5

9

B

5

3

7

C

6

4

5

D

7

2

6

      Using Johnson’s rule, find the optimal sequence.     