Consider the following jobs and their processing times at corresponding machines:-
Job
Duration (Hours)
m/c 1
m/c 2
m/c 3
t1
t2
t3
A
13
5
9
B
3
7
C
6
4
D
2
Using Johnson’s rule, find the optimal sequence.