The network diagram of a project is given in Figure below. The activity times in days are shown on the arcs.
Determine
(i) Critical path and critical path time;
(ii) Total float and free float of activity 1-4.
(iii) If due to unavoidable reasons activity
(1-3) takes 6 days instead of 4, find the change in the critical path.