The network diagram of a project is given in Figure below. The activity times in days are shown on the arcs.

      Determine

(i)     Critical path and critical path time;  

(ii)    Total float and free float of activity 1-4.

(iii)   If due to unavoidable reasons activity
(1-3) takes 6 days instead of 4, find the change in the critical path.