0 votes
51 views
asked in IM&OR by (215k points)

Statement for Linked Answer Q1 & Q2

For a particular project, eight activities are to carried out. Their relationships with other activities and expected durations are mentioned in the table below.

Activity

predecessors

Duration  (in days)

a

-

3

b

a

4

c

a

5

d

a

4

e

b

2

f

d

9

g

c,e

6

h

f,g

2

 

  1. The critical path for the project is                                                

      (a) a – b – e – g – h

      (b) a – c – g – h

      (c) a – d – f – h

      (d)  a – b – c – f – h

      2. If the duration of activity “f” alone is changed from 9 to 10 days, then the                                                                                           

      (a) critical path remains the same and the total duration to complete the project changes to 19 days

      (b) critical path and the total duration to complete the project remains the same

      (c) critical path changes but the total duration to complete the project remains the same

      (d)  critical path changes and the total duration to complete the project changes to 17 days.

Please log in or register to answer this question.

Related questions

Welcome to Q&A discussion forum, where you can ask questions and receive answers from other members of the community.

10.4k questions

274 answers

26 comments

14.6k users

...