0 votes
81 views
asked in IM&OR by (215k points)
edited by

Common Data for Question 01 & 02

Consider the following network

The optimistic time most likely time and pessimistic time of all the activities are given in the table below:

   Activity

   To

    Tm

     Tp

Te = $\frac{T_{o}+4T_{m}+T_{\rho }}{6}$

$\sigma = \frac{T_{\rho }-T_{o}}{6}$

$\sigma ^{2}=\left ( \frac{T_{\rho }-T_{o}}{6} \right )^{2}$

1 – 2

1

2

3

2

1/3

1/9

1 – 3

5

6

7

6

1/3

1/9

1 – 4

3

5

7

5

2/3

4/9

2 – 5

5

7

9

7

2/3

4/9

3 – 5

2

4

6

4

2/3

4/9

5 – 6

4

5

6

5

1/3

1/9

4 – 7

4

6

8

6

2/3

4/9

6 – 7

2

3

4

3

1/3

1/9

 

  1. The critical path duration of the network (in days) is                                                                                                                           

      (a) 11                                                                  (b) 14                 

      (c) 17                                                                  (d)  18

 

     2.  The standard deviation of the critical path is                                 

      (a) 0.33                                                               (b) 0.55

      (c) 0.77                                                               (d)  1.66

Please log in or register to answer this question.

Related questions

Welcome to Q&A discussion forum, where you can ask questions and receive answers from other members of the community.

10.4k questions

274 answers

26 comments

14.7k users

...