0 votes
51 views
asked in IM&OR by (215k points)

Statement for Linked Answer Q01 & 02

Consider a PERT network for a project involving six tasks (a to f)

Task

Predecessor

Expected task time (in days)

Variance of the task time (in days2)

    a

      -

     30

         25

    b

      a

      40   

       64

     c

      a

      60

       81

    d

      b

     25

       9

      e

      b, c

    45

      36

      f

     d, e

     20

           9

 

  1. The expected completion time of the projects is                                                                                                                        

      (a) 238 days                    (b) 224 days                (c) 171 days                    (d) 115 days

 

    2. The standard deviation of the critical path of the project is                                                                                                        

      (a) $\sqrt{151}$  days                  (b) $\sqrt{155}$days               (c) $\sqrt{200}$  days                  (d) $\sqrt{238}$ days

Please log in or register to answer this question.

Welcome to Q&A discussion forum, where you can ask questions and receive answers from other members of the community.

10.4k questions

274 answers

26 comments

14.7k users

...