0 votes
799 views
asked in im&or by (215k points)
The variance of the completion time for a project is the sum of variances of

(a) All activity times

(b) Non-critical activity times

(c) Critical activity times

(d) Activity times of first and last activities of the project

Please log in or register to answer this question.

Welcome to Q&A discussion forum, where you can ask questions and receive answers from other members of the community.

10.4k questions

274 answers

26 comments

15.2k users

...