0 votes
31 views
asked in im&or by (215k points)
If the earliest strating time for an activity is 8 weeks the latest finish time is 37 weeks and the duration time of the activity is 11 weeks than the total float is equal to

(a) 18 weeks                                      (b) 14 weeks

(c) 56 weeks                                      (d) 40 weeks