Thirty identical machines are being used by a manufacturing concern. On the average a machine runs for 25 days after repair between two consecutive breakdowns. The average cost due to loss of production is rupees 200 per breakdown. If standby machines are used, the daily cost per machine is rupees 40.
Determine the optimum number of standby machines. A constant failure rate may be assumed.